16 Jul 2025

Behind the Build - July Edition

This month, we poured the roof slab on Tower One, a major milestone in Cascade’s construction journey. With 75% of residences now sold, momentum continues to build both onsite and off. Step behind the scenes and see how Cascade is coming to life.

Tower One: Structure complete with roof slab now poured.

 

Tower Two: Level 12 slab poured.

 

Bathrooms on lower levels are nearing completion.

A first-look inside a ground floor 3 Bedroom apartment kitchen with Caesarstone 

benchtops, Miele appliances and timber joinery.

Plasterboard being cut and installed in Tower Two.

Balustrades being measured and installed. 

Waterproofing being carried out in upper level bathrooms.

Our travertine-look, large format floor tiles being installed in a 2 Bedroom apartment.

Slab being poured for the villas and wellness amenities.

Onsite Display Now Open

Experience Cascade firsthand at our new display suite. 

 

Location: 116 Laver Drive, Robina

 

Tuesday & Thursday: 2pm – 5pm and Saturday & Sunday: 10am – 1pm. Or by private appointment.

Back to all News

Enquire Now

Call Kyle 0499 902 874
Or submit your details to receive further information.

Onsite sales display now open

7 days from 2pm - 4pm

116 Laver Drive, Robina QLD 4226.